Document the requirement, observed variance, disposition, corrective action and verification. This template keeps the visible record, required verification and responsible follow-up together.
TruInspector editorial team · Reviewed October 8, 2026
Document the requirement, observed variance, disposition, corrective action and verification. Start with the exact inspection purpose and location, document only what the submitted evidence supports, and keep measurements, testing or professional determinations clearly marked for field review.
FIELD WORKFLOW
Use this template
1
Record project, area, grid, level, trade and construction stage.
2
Identify the approved drawing, specification or submittal when applicable.
3
Capture overall assembly, interfaces and close detail before work is concealed.
4
Record required dimensions, tests, inspections and professional determinations as separate evidence.
5
Assign responsibility, due date, disposition and closeout verification.
PRINTABLE WORKSHEET
Fields to complete
Construction Non-Conformance Report Template
01Project, property or facility identifier
Record:
02Location and inspection purpose
Record:
03Observation supported by photos or video
Record:
04Required action, owner and due date
Record:
05Verification and closeout evidence
Record:
DOCUMENTATION EXAMPLE
A finding that stays within the evidence
Asset or area
Building penetration
Visible condition
A visible service penetration appears incompletely sealed at the photographed wall. Assembly rating, approved system and concealed installation were not established.
Recommended action
Identify the rated assembly and approved penetration system, compare the field installation with its listing, complete authorized corrective work and retain closeout evidence.
Make the report easier to review
Use a short finding title, identify the exact location and place the strongest evidence beside the written observation. Explain the recommended next step in practical order: verify, make safe when needed, correct the confirmed condition and retain completion evidence.
Keep sources tied to the finding
Record the jurisdiction, adopted edition, contract, company procedure or customer-supplied requirement that applies. A source link helps the reviewer locate the material; it does not prove that every requirement applies to the photographed condition.
State what the evidence cannot prove
Photo review does not provide engineering design approval, material acceptance, structural certification or replacement for required inspections and testing.
STARTING SOURCES
References for qualified review
Confirm the current edition, jurisdiction and applicability before relying on a requirement.